Sweetheart dam nears federal permit

The Sweetheart Lake Hydroelectric Project is nearing the end of its long federal permitting process. On the last day of May, the Federal Energy Regulatory Commission issued its final environmental impact statement for the 111-foot dam and powerhouse planned for a lake southeast of Juneau.

“Based on our analysis,” the report stated, “we recommend licensing the project as proposed by Juneau Hydro with some staff modifications and additional measures.”

Juneau Hydropower Inc. (JHI), the company backing the project, said in a press release that the release of the EIS allows the company “to begin the process to start construction later this year.”

The environmental impact statement is not the same as a license to build a dam, but it is the most significant part of the licensing process.

JHI envisions a dam at the natural outlet of Lower Sweetheart Lake, whose level would be raised to become a reservoir for the project. A two-mile underground tunnel would convey water from the lake to a powerhouse near sea level at the mouth of Sweetheart Creek.

That powerhouse would produce 19.8 megawatts of electricity — a quarter of Juneau’s 2013 electrical load — from three generators. Overland and undersea cables would connect the powerhouse to the existing power transmission lines that link the city to the Snettisham hydroelectric project. The connection would be made to avoid the avalanche-prone sections of that line.

The federal analysis concluded, “power from the project would help meet a need for power, from a clean and renewable source, in the Juneau area in both the short and long term. … Displacing the operation of non-renewable facilities may avoid some power plant emissions, thus creating an environmental benefit.”

The analysis recommended some minor changes to JHI’s construction and operation plan to minimize the effect of the project on area wildlife. One change of note calls for the dam’s operators to consult with the Alaska Department of Fish and Game to develop a plan that would release water from the dam in pulses.

In Sweetheart Creek, below the dam, this would have the effect of mimicking the natural ebb and surge caused by rainfall. Studies have indicated that pulsed flows may improve salmon survival rates.

Sweetheart Lake is currently stocked with sockeye salmon (fish cannot return to the lake due to waterfalls below the lake’s exit) and JHI’s salmon plan calls for the release of at least 21,000 smolt into Sweetheart Creek annually.

JHI would also be required to implement a bear-management plan to reduce the effects of construction on the animals that forage in the creek, and it would be required to grant public access to the dock and boat ramp constructed at the dam site.

Power from the project is intended to go to Kensington Gold Mine north of Juneau. Previous studies have indicated there is a need for about 10 megawatts of electricity at the mine, which currently operates on diesel generators.

JHI intends for the remaining project electricity to power a “district heating system” in downtown Juneau that would displace oil-fired boilers. Instead, those boilers would be connected to hot water piping from a central, hydroelectric-powered heating plant.

Alaska Electric Light and Power, while not formally opposing the project, has raised questions about JHI’s intentions and ability to accomplish its stated goals.

In a letter dated May 25, AEL&P chairman Dennis Vermillion pointed out that JHI’s efforts to license a high-voltage power line between Juneau and Kensington Gold Mine have been put on hold until JHI’s subsidiary, Lynn Canal Transmission, reveals its financial documents.

“The need for power is a significant consideration in conducting analyses regarding a proposed project and deciding whether to grant a license,” Vermillion wrote.

More in News

(Juneau Empire file photo)
Aurora forecast through the week of Nov. 10

These forecasts are courtesy of the University of Alaska Fairbanks’ Geophysical Institute… Continue reading

Tlingit “I Voted” stickers are displayed on a table at the voting station at the Mendenhall Mall during early voting in the Nov. 5 general election. (Laurie Craig / Juneau Empire file photo)
Ranked choice voting repeal coming down to wire, Begich claims U.S. House win in latest ballot counts

Repeal has 0.28% lead as of Saturday, down from 0.84% Thursday — an 895-vote gap with 9,000 left to count.

(Mark Sabbatini / Juneau Empire file photo)
Juneau man arrested on suspicion of murdering 1-month-old infant after seven-month investigation

James White, 44, accused of killing child with blunt blow to head in a motel room in April.

A map shows properties within a proposed Local Improvement District whose owners could be charged nearly $8,000 each for the installation of a semi-permanent levee to protect the area from floods. (City and Borough of Juneau map)
Hundreds of property owners in flood zone may have to pay $7,972 apiece for Hesco barrier levee

City, property owners to split $7.83M project cost under plan Juneau Assembly will consider Monday.

Dan Allard (right), a flood fighting expert for the U.S. Army Corps of Engineers, explains how Hesco barriers function at a table where miniature replicas of the three-foot square and four-foot high barriers are displayed during an open house Thursday evening at Thunder Mountain Middle School to discuss flood prevention options in Juneau. (Mark Sabbatini / Juneau Empire)
Residents express deluge of concerns about flood barriers as experts host meetings to offer advice

City, U.S. Army Corps of Engineers say range of protection options are still being evaluated

U.S. Geological Survey geologist Geoffrey Ellis stands on Oct. 29 by a poster diplayed at the University of Alaska Fairbanks that explains how pure hydrogen can be pooled in underground formations. Ellis is the leading USGS expert on geologic hydrogen. He was a featured presenter at a three-day workshop on geologic hydrogen that was held at UAF. (Yereth Rosen/Alaska Beacon)
Alaska scientists and policymakers look to hydrogen as power source of the future

The key to decarbonization may be all around us. Hydrogen, the most… Continue reading

(Michael Penn / Juneau Empire file photo)
Police calls for Wednesday, Nov. 13, 2024

This report contains public information from law enforcement and public safety agencies.

Gov. Doug Burgum of North Dakota speaks to reporters at the National Constitution Center in Philadelphia in advance of the presidential debate between former President Donald Trump and Vice President Kamala Harris, Sept. 10, 2024. President-elect Trump has tapped Burgum to lead the Interior Department, leading the new administration’s plans to open federal lands and waters to oil and gas drilling. (Kenny Holston/The New York Times)
Trump nominates governor of North Dakota — not Alaska — to be Interior Secretary

Doug Burgum gets nod from president-elect, leaving speculation about Dunleavy’s future hanging

Most Read