Prudhoe Bay pipeline repair cost bumped up

Posted: Friday, October 26, 2007

JUNEAU - BP PLC said Wednesday that costs to replace approximately 16 miles of pipeline at Prudhoe Bay has increased slightly to as much as $260 million.

Sound off on the important issues at

That figure would be a $10 million increase - or about 4 percent - over original estimates provided 15 months ago.

"The one uncertainty is that there is inflationary costs associated with labor costs," said Mike Utsler, BP's senior vice president for greater Prudhoe Bay operations, who said the costs could range from $255 million to $260 million.

Utsler's comments came as he updated the state Senate Resources Committee, which is reviewing Gov. Sarah Palin's bill to raise oil taxes during a special legislative session.

BP began rebuilding the 16-mile transit pipeline system last year after the company discovered corrosion that forced a partial shutdown at Prudhoe Bay, the nation's largest field responsible for about 8 percent of the nation's production.

No one among the seven-member Senate committee seemed to find BP's 2 percent to 4 percent cost boost on the Prudhoe Bay rebuilding project to be onerous, especially when other companies report 50 percent increases in costs related to construction since 2005.

"They've been working on it for going on two years, so it's understandable that there would be some inflationary costs. I just don't want the state to pay for any of it," Wagoner said of BP's increase.

North Slope producers have spent the last three days imploring lawmakers to rethink any rate increase, the second in as many years, because it could jeopardize future investment.



CONTACT US

  • Switchboard: 907-586-3740
  • Circulation and Delivery: 907-586-3740
  • Newsroom Fax: 907-586-3028
  • Business Fax: 907-586-9097
  • Accounts Receivable: 907-523-2230
  • View the Staff Directory
  • or Send feedback

ADVERTISING

SUBSCRIBER SERVICES

SOCIAL NETWORKING