http://racerealty.com/

TransCanada still negotiating on pipeline

Posted: Wednesday, December 08, 2010

JUNEAU - TransCanada Corp. says it may not meet its target of securing binding agreements by year's end for a major natural gas pipeline in Alaska, but the company remains optimistic about the prospects for its project.

TransCanada spokesman James Millar told The Associated Press on Tuesday officials are pleased with negotiations with gas producers so far, but the process is complicated and takes time. In spite of an official's earlier stated target of having precedent agreements by year's end, he said TransCanada's concern is less on an arbitrary clock and more on ensuring that negotiations are undertaken prudently.

He said it's too early to say whether there will be a need for another open season, during which gas producers are courted and shipping commitments are sought.

"We remain optimistic," Millar said.

Negotiations focused on resolving conditions within the company's control have been under way since July, when TransCanada ended a three-month open season. TransCanada has not identified the bidders on the project, saying only it received multiple bids from "major industry players and others."

TransCanada, based in Alberta, Canada, is working with Exxon Mobil Corp. to advance a pipeline project that would bring gas from Alaska's harsh, prodigious North Slope to market. It's doing so with a pledge of up to $500 million in state aid, as part of its exclusive license under the Alaska Gasline Inducement Act - a legacy initiative of former Gov. Sarah Palin.

The project faces competition from Denali-The Alaska Gas Pipeline, a joint effort of BP PLC and ConocoPhillips that is moving ahead without state support. Denali has said it hopes to complete negotiations early next year.

Larry Persily, the federal coordinator for Alaska natural gas pipeline projects, said people shouldn't read anything into it if TransCanada misses its self-imposed deadline for agreements. He said he wouldn't be surprised if Denali's deals came later than expected, too.

Persily said agreements are big deals given once shippers sign them, they're essentially assuming part of future development costs. Proposed projects have ranged in price from $20 billion to $41 billion.

"If a year from now they still don't have precedent agreements, that's bad," he said. "It's good they're still working on it."

It's widely believed only one pipeline will be built, if one gets built at all. Oil and gas company officials have said they'd seek long-term fiscal certainty from the state, a term outside the control of the pipeline companies and one that Gov. Sean Parnell's administration has said they'd have to demonstrate a clear need for.

Millar said the message the company's getting from Parnell is that he still has confidence in the Inducement Act but that officials want to talk with his new commissioners on the issue.

Parnell, who took over for Palin when she quit last year and was sworn in for his first full term Monday, sees the competition as a good thing and said he's committed to seeing that a pipeline gets filled.



CONTACT US

  • Switchboard: 907-586-3740
  • Circulation and Delivery: 907-523-2295
  • Newsroom Fax: 907-586-3028
  • Business Fax: 907-586-9097
  • Accounts Receivable: 907-523-2270
  • View the Staff Directory
  • or Send feedback

ADVERTISING

SUBSCRIBER SERVICES

SOCIAL NETWORKING