Glenfarne takes majority stake of Alaska LNG Project, will lead development

The Alaska Gasline Development Corporation announced Thursday they had reached an agreement with the New York-based company.

The Alaska Gasline Development Corporation and New York-based Glenfarne Group have reached an agreement for Glenfarne to develop the Alaska LNG Project, AGDC announced Thursday. Glenfarne Founder and CEO Brendan Duval said he expects a final investment decision before the end of the year.

First reported by KDLL 91.9 FM, AGDC’s board of directors at a special meeting on Thursday adopted a resolution authorizing AGDC President Frank Richards to execute an agreement that has been negotiated over recent months. The conditions of that agreement are confidential.

A press release from AGDC Thursday evening says that Glenfarne, via a new affiliate called Glenfarne Alaska, will take on a majority stake in 8 Star Alaska, an AGDC subsidiary that was established to maintain ownership of the project. Glenfarne will own 75%, while AGDC and the state will retain the remaining 25%.

ADVERTISEMENT
0 seconds of 0 secondsVolume 0%
Press shift question mark to access a list of keyboard shortcuts
00:00
00:00
00:00
 

Glenfarne was founded in 2011 by Duval and has pointed to LNG as the “environmentally sensible” solution to fill the need for global energy while renewables are developed to combat climate change. Alaska is the third major LNG project under their purview, as the company is also developing LNG projects in Texas and Louisiana.

The agreement covers the full development of the Alaska LNG Project, which has been divided into multiple phases to account for the high costs of development. The three “subprojects” include an 807-mile 42-inch pipeline, an LNG export terminal in Nikiski expected to output up to 20 million tons of LNG per year, and a North Slope-based carbon capture plant that will “remove and safely store” 7 million tons of carbon dioxide annually, the release says.

While the complete project has been projected to cost $44 billion, AGDC has touted a report by Wood Mackenzie that says phase one, the pipeline, could be constructed for $10.8 billion and provide gas to Alaskans looking at a looming shortfall of natural gas supply.

“In light of steadily declining gas production from Cook Inlet, which has historically been Alaska’s primary in-state natural gas basin, phase one of the project will kick off immediately, prioritizing the development and final investment decision of the pipeline infrastructure needed to deliver North Slope gas to Alaskans as rapidly as possible,” the release reads.

After the agreement was announced, Richards, Duval and Alaska Gov. Mike Dunleavy held a press conference from Tokyo, Japan, early Friday morning because of the time difference. Dunleavy said he’s been traveling to several Asian countries to promote Alaska gas.

While some Asian countries have publicly expressed interest in Alaska LNG, none have signed any binding agreements to purchase gas. Dunleavy said that, while previous developments aren’t binding, “it’s the kickoff of deeper conversation.” He said he’s seen forward momentum with Taiwan, Thailand, Korea and Japan.

The Alaska LNG Project, Dunleavy said, has cleared through legal challenges, obtained its permits and rights of way, has support from the federal government and can meet demand in Asia.

“A lot of us are feeling confident that this is going to move to a concrete pipeline being built within two and a half years that will bring gas to Alaskans,” he said. “I think we’re poised to hear more good news.”

Richards said that Thursday’s agreement “was essentially us providing Glenfarne that 75% leadership role to be able to take this project forward.” Gas from the project is projected to start reaching Alaskans “in the very near term,” before construction and operation of the full project. Richards said that will bring jobs and revenue to Alaska.

Duval said that the Alaska LNG Project is “a standalone, attractive project.” He said that Glenfarne has advanced the project without the previously reported $50 million design backstop from the state because they want to move more quickly than it could have coalesced.

The project will announce a funding “consortium” in the coming weeks before the front-end engineering and design study, which is expected to be completed in the third quarter of 2025, before final investment decision in the fourth quarter, Duval said. A pipeline tariff on the gas being moved will “underwrite” the decision to move forward, but he said the cost “we think, is reasonable.”

The project will be funded by “private sector dollars,” he said, with the enhancement of a federal loan guarantee. Design and construction will not be funded by other governments, who won’t get involved until the latter phases when the export facility is constructed. There is some “appetite” from the U.S. government to accelerate the project, with meetings underway, but Duval said he had nothing to announce Friday.

“This project doesn’t need subsidizing,” he said. “This will be funded for profit.”

Sen. Jesse Bjorkman and Rep. Bill Elam, both R-Nikiski, on Thursday night both celebrated the development.

“This is a very exciting step forward that all Alaskans can celebrate,” Elam said in a press release from the Alaska House Republican caucus. “This is a hard-won victory that puts Alaskans — and my district — at the heart of our state’s energy future. It means lower costs, new revenue, and jobs. I’m ecstatic to see it moving ahead.”

The next development for the project, Duval said, will be the start of the front-end engineering and design study, “here in the coming weeks.” That work will extend for “approximately six months,” and the result will inform the timing of the final investment decision.

Reach reporter Jake Dye at jacob.dye@peninsulaclarion.com.

More in News

(Juneau Empire file photo)
Aurora forecast through the week of March 23

These forecasts are courtesy of the University of Alaska Fairbanks’ Geophysical Institute… Continue reading

A Capital City Transit Center electric bus (left) and diesel bus (right) wait for passengers at the Downtown Transit Center on Friday, March 7, 2025. (Jasz Garrett / Juneau Empire)
Capital Transit is constructing a charging station for its new electric buses

Capital Transit superintendent says fleet offering better experience than first electric bus received in 2020.

Signs at the front of the Alaska State Capitol on Sunday, Dec. 8, 2024, indicate a designated entrance for legislators and their staff, and direct members of the public to a separate door. The signs were in anticipation of a security screening policy that was put on hold, but on Monday a similar policy was approved by the Legislative Council. (Mark Sabbatini / Juneau Empire file photo)
Airport-style security screening coming soon to Alaska State Capitol after Legislative Council’s OK

“It will probably be a couple weeks before it’s all in place,” says Rep. Sara Hannan, the council’s chair.

William Steadman, a Juneau resident, has pleaded guilty to a federal charge of producing child pornography, according to law enforcement officials. (Photo provided by the U.S. Department of Justice)
Juneau man faces minimum 25-year sentence after guilty plea to federal child pornography charge

William Steadman, 35, has prior child pornography conviction from 2018.

(Michael Penn / Juneau Empire file photo)
Police calls for Saturday, March 29, 2025

This report contains public information from law enforcement and public safety agencies.

(Michael Penn / Juneau Empire file photo)
Police calls for Friday, March 28, 2025

This report contains public information from law enforcement and public safety agencies.

(Michael Penn / Juneau Empire file photo)
Police calls for Thursday, March 27, 2025

This report contains public information from law enforcement and public safety agencies.

Angie Flick (center), finance director for the City and Borough of Juneau, explains to Assembly members the financial impacts of various adjustments to the mill rate during a Finance Committee meeting on Wednesday, May 22, 2024. (Mark Sabbatini / Juneau Empire file photo)
Proposed CBJ budget eyes increase to 10.19 mills due to school building takeover, other costs

Unknowns as Assembly begins two-month process are contract negotiations, federal funding.

Most Read