Washington halts Seattle tunnel project over safety concerns

SEATTLE — Washington transportation officials and Gov. Jay Inslee on Thursday halted all digging by Seattle’s tunnel-boring machine until the contractor determines what caused a large sinkhole to form over the area where the machine was operating.

“I have great concerns regarding public safety if the contractor were to move forward without addressing the root causes of this sinkhole,” Inslee said during a news conference. “We must continue to protect the public safety.”

The sinkhole, measuring 35 feet long, 20 to 25 feet wide and 15 feet deep, appeared Tuesday night. The contractor, Seattle Tunnel Partners, filled it with concrete, according to transportation officials. Officials also cited an accident on Tuesday when a barge carrying excavated soil began to tip and dropped material into the water. The spill posed a hazard to the tunnel workers and the public, officials said in a letter to the contractor.

Transportation Secretary Lynn Peterson said they ordered the work stoppage “to ensure that the contractor has the right protocols in place to proceed with their work safely.”

The tunnel-boring machine called Bertha will not be allowed to resume until the contractor’s analysis and work plans satisfy the state’s experts, she said.

A tunnel along Seattle waterfront was the plan of choice to replace the Alaskan Way Viaduct after it was damaged in a 2001 earthquake. But Bertha broke down about two years ago and only recently resumed operations after repairs were completed.

“I want to remind everyone that replacing the viaduct is critical to public safety,” Peterson said. “The tunneling work must proceed, but it must proceed safely.”

State officials conducted a manual survey of the viaduct and found no new movement, both Peterson and Inslee said.

“I want to stress the very reason the Legislature proceeded with this project originally was to tear down the seismically vulnerable viaduct and fundamentally ensure public safety,” Inslee said.

This was the second delay this week.

Digging in the tunnel was stopped on Tuesday after a barge carrying soil that was pulled from the tunnel began to lean to one side and spilled some of its load into Elliott Bay before drifting into a nearby pier. In order to prevent damage to the conveyor system, workers released the barge from its moorage at Terminal 46. That’s when some of the soil spilled into the bay.

Tunnel excavation was put on hold while the contractor inspected the terminal and pier for damage.

The original completion date for the new Seattle tunnel was the fall of 2015. When the machine started moving again, Project Manager Chris Dixon said they’ll finish the tunneling phase by January 2017 and the double-decker highway project will open to traffic in April 2018 — almost three years late.

It’s not known how the latest work stoppage will affect those plans.

___

AP reporter Rachel La Corte contributed from Olympia, Washington.

____

Follow Martha Bellisle at https://twitter.com/marthabellisle . Her work can be found at http://bigstory.ap.org/journalist/martha-bellisle .

More in News

(Juneau Empire file photo)
Aurora forecast through the week of Dec. 29

These forecasts are courtesy of the University of Alaska Fairbanks’ Geophysical Institute… Continue reading

In an undated image provided by Chris Miller, an image of the northern lights in Juneau shows what a camera with a longer exposure captures. As astrotourism booms, the northern lights get a boost from digital photography. (Chris Miller via The New York Times)
Is the aurora borealis really that mind-blowing? Or is it just your cellphone photos?

In August, over a calm Michigan lake, Karl Duesterhaus, 34, of Chicago,… Continue reading

The Juneau School District administrative office inside Thunder Mountain Middle School on Tuesday. (Mark Sabbatini / Juneau Empire)
Juneau School District, after further review, says it was affected by PowerSchool data breach

Information at risk may include parents, student and staff contact information and addresses.

A map shows where five proposed totem poles would be placed at the Mendenhall Glacier Visitor Center. (U.S. Forest Service)
Five new totem poles proposed at Mendenhall Glacier Visitor Center as part of stewardship agreement

Open house Wednesday to discuss project intended to “represent several Tlingit and Haida clans.”

Kristin Garot asks a question to members of Juneau’s legislative delegation at a town hall in the Dzantik’i Heeni school commons on Monday, Jan. 13, 2025. (Jasz Garrett / Juneau Empire)
Expect tighter budget, but more say in how the money is spent, local legislators say

Juneau lawmakers cite familiar issues of education, pensions as priorities at pre-session town hall

Mike Bethers and his wife, Astrid, turn over two fish to Alysha Reeves, dock chair at the Auke Nu weighing station during the final day of the 78th annual Golden North Salmon Derby on Sunday, Aug. 11, 2024. (Mark Sabbatini / Juneau Empire file photo)
Dozens of Board of Fisheries proposals affecting Southeast Alaska reviewed by Upper Lynn Canal AC

159 proposals for meeting between Jan. 28 and Feb. 9 involve hatcheries, crabs, rockfish and more.

(Michael Penn / Juneau Empire file photo)
Police calls for Saturday, Jan. 11, 2024

This report contains public information from law enforcement and public safety agencies.

(Michael Penn / Juneau Empire file photo)
Police calls for Friday, Jan. 10, 2024

This report contains public information from law enforcement and public safety agencies.

(Michael Penn / Juneau Empire file photo)
Police calls for Thursday, Jan. 9, 2024

This report contains public information from law enforcement and public safety agencies.

Most Read